Milder weather has enabled us to make some good progress over the past week. The floor slabs for the stage area, storage areas and mezzanines were poured last week so that finishes the floor slabs. Metal stud walls continue to go up and door frames installed in the walls. The concrete block walls were finished so the only masonry left is the exterior brick. Plywood sheathing has been installed on the classroom wing and the wood trusses are being installed this week. The roof structure over the gym is getting finished up this week too.
Monday, February 22, 2010