Pray for dry weather! Preparation for pouring the concrete floor slab is going on today with the hope of starting the concrete early tomorrow morning. The stone that goes under the slab was put in last week and the plastic vapor barrier and metal wire reinforcing is being installed this morning. Regardless of the wet weather, the work on the metal stud walls continues and the steel bar joists that frame the floors for the mezzanine areas are being installed. The ceiling bar joists that are the framing for the gymnasium area roof were delivered yesterday and will be installed once the floor slab has been poured. A lot of underground work continues down by the new and existing mechanical rooms as the contractors prepare that area to install the new cooler tower.