Our contractor walked by my window and tapped on it. He likes to do that when he needs me to look at something. This time I looked up and he was holding two thumbs up. The structural steel frame is basically finished - the crane is leaving. That's not the only exciting news. Metal stud walls are starting to go up as well. They started this morning just outside the back door and will be building the wall that faces the modular buildings this week. The building pad has finally dried out enough and the stone that goes under the floor slab will start going in tomorrow. The first part of the concrete slab will be poured this Friday if all goes according to plan. The roof joists are scheduled to be delivered next Tuesday and those should start going up later next week. Much to give thanks for!