Wednesday, August 4, 2010

Update 08.04.10











Just over a month to go and things are progressing well. Biggest snag at the moment is getting York County to sign off on the electrical portion of things so that we can turn on the power. As of today, we should get the go ahead tomorrow on that and if so, we'll be shooting to get the power on early next week. This will allow us to turn on lights and get the air conditioning running so the the building gets climate controlled. Then we'll be able to install things like carpet, doors, ceiling tiles, etc. Good progress on the lobby addition as it is basically dried in now and interior wall work is getting done. We should be ready for drywall in there pretty soon. Toilet partitions and mirrors were installed this week in both bathrooms.

1 comment:

Mark said...

Wonderful!! Do we have a target date for COA?