Things continue to dry out and progress goes well. The work on the pond area is almost complete. The subcontractor was out today raking up twigs and smoothing out the re-disbursed top soil. Work on the roof panels continues with most of the panels already installed on the gym roof. The vinyl siding has been ordered and is supposed to start going up in a week or so. Still waiting on the mortar for the brick and that will start going up as soon as it arrives. Lots of metal stud work going on in the gym area as workers shape up the tall walls around the gym. Lots of plumbing and mechanical work going on as well.