Tuesday, December 8, 2009
Update 12.8.09
And more rain....yet progress. Seems like we are getting rain every couple of days which is just enough to hinder progress. The contractor has been able to keep moving in some areas despite the lingering moisture and constant rain. The footings have been finished now and the foundation wall masonry is getting close to completion. We just need dry weather to dry out the building pad so that the floor slab can be poured. Structural steel is scheduled to be delivered next week and if things go well with York County this week, we will be erecting the steel next week as well. Continue to pray for dry weather!
Subscribe to:
Post Comments (Atom)
2 comments:
Is September 1 still doable?
Yes, in fact they are telling me early August now. :)
Post a Comment