Update 11.3.09







Wet but still moving along - that about describes the project today. After several days of rain, the footing work continues despite the muddy conditions. Lots of digging in the morning and then the concrete comes in the afternoon to fill up the holes. Loads of concrete masonry blocks were delivered today and I'm told that the masonry work will begin on Thursday morning. The work of putting a new drainage line across the driveway was completed this weekend and the new waterline for a new fire hydrant is underway.