Met with our architect and site engineer this morning to go over the final changes. Lots of dotting i's and crossing t's but nothing major. Plan is to get the changes to the site drawings done and have a final internal review on Monday (6/8) afternoon and re-submit the site plan to York County on Tuesday or Wednesday. We are still on track to start handing out drawings and specifications to general contractors early next week as well.